Vermont Agency of Transportation This weekly report is a list of planned construction activities that will have traffic impacts on state highways throughout Vermont. Please remember to drive safely in all work zones. Lives depend on it.
Interstates
I-89 Brookfield – Montpelier – A resurfacing project continues in the southbound lanes between Exits 5 and 8. Operations will require lane reductions in the vicinity of active construction, with speed reductions to 55 mph when lane closures are in effect.
I-89 Richmond – A culvert repair project is underway. Motorists will encounter a one-mile-long lane closure in both travel directions just south of Exit 11 as southbound traffic is merged to the northbound lane using a crossover. Please pay attention to signage in the area and merge early.
I-89 Sharon – A bridge rehabilitation project continues. Traffic is reduced to one lane in each direction as crossovers are being utilized. Motorists - be aware of a work zone speed reduction.
I-89 White River Junction – Our partners at NHDOT are working on a multi-year bridge replacement project on I-89 over the Connecticut River. Motorists should expect daily lane closures and speed reductions over the bridge.
I-91 Bradford – Northbound and southbound lane closures have been implemented near Exit 16 for preventative maintenance repair to bridges. A speed limit reduction to 55 mph through the work zone is in place.
I-91 Fairlee – St. Johnsbury – Interstate travel will continue to be reduced to one lane in both directions for preventative maintenance repairs to multiple bridges. Speed limit and lane width restrictions are in effect.
I-91 Lyndon – Barton – No work is expected this week on an interstate resurfacing project, but motorist should expect travel on uneven lanes and milled surfaces.
I-91 Ryegate – St. Johnsbury – A northbound resurfacing project is underway. There will be a single lane closure between Exits 17 and 20 as crews continue fog sealing the shoulders and begin paving. Minimal delays.
I-91 Weathersfield – A bridge deck replacement project continues at Exit 8. Lane and speed reductions are in effect as southbound traffic is merged to the northbound bridge using a crossover. Expect intermittent periods of flagged traffic along VT 131 under the bridge.
I-91 Westminster – A bridge deck replacement project over VT 121 is underway. I-91 Southbound has been reduced to one lane over the bridge. A speed reduction to 55 mph is in place within the project area. Fines are doubled for speeding within the construction zone.
Around the State
Braintree – Preliminary construction activities for a bridge deck replacement project will continue next week with one-way alternating traffic patterns being implemented as needed on VT 12 approximately 5 miles north of the intersection with VT 66.
Brattleboro – Newfane – A series of culvert replacements continues along VT 30. Motorists may encounter alternating one-way traffic in the area.
Burlington – A paving project is underway along U.S. 2/Main Street from South Willard St. to I-89, and along North Willard St. to the intersection with Riverside Ave. Nighttime work hours are 7 p.m. – 6 a.m., Sunday through Thursday. Motorists should expect one-way alternating traffic during nighttime operations.
Burlington, Shelburne Street Roundabout – Detour routes will remain in place 24/7 for motorists traveling along U.S. 7/Shelburne Street between Flynn Ave and Howard St. and South Willard St. between Howard St. and Shelburne St.
The U.S. 7/Shelburne Street detour will divert traffic along Howard St., Pine St., and Flynn Ave (southbound and northbound) to avoid delays on weekdays between 9 a.m. - 3 p.m. Shelburne St. will remain open to local traffic.
Calais – Multiple bridge replacement projects are underway along VT 14 beginning approx. 7.6 miles north of its intersection with U.S. 2. Motorists should expect speed reductions and alternating one-way traffic controlled by flaggers during the day and a temporary signal at each bridge during non-work hours.
Chester – A bridge deck replacement project is underway on VT 103 just south of Smokeshire Rd. Speed and lane width reductions are in effect throughout the project area. VT 103 Bridge #16 is closed through October 2022. Traffic will be maintained on a temporary bridge.
Chester – Springfield – A roadway project is underway on VT 11 between VT 103 in Chester and VT 106 in Springfield. Expect one-way alternating traffic at multiple points along this route, with moderate delays in the vicinity of paving operations. Please add extra time to travel plans.
Essex – Colchester – A resurfacing project resumes along VT 2A. Motorists will encounter one-way alternating traffic on Sunday – Thursday nights from 7 p.m. to 6 a.m.
Essex Junction – A series of rail replacements continues in connection with the local Crescent Connector project. VT 117 (Maple Street) is closed at the rail crossing location just east of the Five Corners intersection until 7 a.m. Tuesday, 07/12. Trucks will be detoured along VT 289, while all other traffic will follow a local signed detour.
Fair Haven – Orwell – Motorists should expect alternating one-way traffic along VT 22A as crews work on paving activities.
Fairlee – VT 25A (Bridge Street) will be closed during the day on 07/11 and 07/12 for drainage work. The roadway will reopen late each afternoon. During the closures, motorists will be detoured along U.S. 5 and VT 25 in Bradford.
Hardwick – A paving project continues on VT 14 and VT 15. Motorists should expect lane closures with alternating one-way traffic along both roadways between 6:30 a.m. and 6 p.m.
Johnson – Morristown – There will be multiple traffic control packages with alternating one-way traffic on VT 15 as crews continue installing guardrail from the Hyde Park Roundabout to Black Farm Rd. and continue ditching and shoulder clean up from the Hyde Park Roundabout to the Hyde Park/Johnson town line. Minimal traffic delays are expected
Montpelier – Several railroad crossing projects are underway. Motorists should expect some flagged one-way alternating traffic at the rail crossing location along U.S. 2 between Gallison Hill Rd. and the traffic circle. Motorists will also encounter flagged traffic at the rail crossing on Pioneer St. off U.S. 2 ahead of its full closure during the week of July 11.
Montpelier – Berlin – A bridge deck replacement project continues along U.S. 2 over the Winooski River at the Montpelier-Berlin town line. Traffic is now directed over a temporary bridge. Motorists may encounter periods of one-way alternating traffic as crews continue removal of the existing bridge.
Montgomery – A set of bridge deck replacements continues along VT 118. Motorists will encounter one-way alternating traffic controlled by flaggers during the day and temporary traffic signals during off-hours between West Hill Rd. and Bank St.
Newfane – The Depot Rd. Arch Bridge over Rock River is closed through Fall 2022. Traffic will be rerouted from the north via Grimes Hill Rd. and from the south via VT 30. Through traffic is not permitted. Grimes Hill Rd. and Dover Rd. (at the intersection with Depot Rd.) are reduced to one lane with signals for the duration of the closure.
North Hero – Grand Isle – Drawbridge construction continues along U.S. 2. A speed reduction remains in place. Mariners: The seasonal operating schedule for the drawbridge is in effect.
Pittsford – Brandon – Motorists should expect one-way alternating traffic patterns on U.S. 7 beginning in the village of Pittsford and continuing north throughout the week as work associated with the paving project continues. Motorcycles are advised to use caution on milled surfaces. Plan on delays.
Plymouth – Bridgewater – A paving project continues along VT 100. Active work zones will be managed with one-lane alternating traffic controlled by flaggers. Work will occur from 6 a.m. – 6 p.m. Monday through Saturday.
Richford – A bridge replacement project is underway along VT 105 approx. one mile south of the intersection of Main St. and River St. Motorists should see little impact to traffic.
A separate culvert replacement project is also underway on VT 105 approx. one mile south of Nickson Rd. Motorists should expect a traffic patten shift with signals directing alternating one-lane traffic through a temporary bypass. A speed reduction to 35 mph will be in effect.
Richmond – Bolton – A resurfacing project continues along U.S. 2. Motorists will encounter areas of one-way alternating traffic and unpaved surfaces as crews work on pavement grinding, ledge removal, and underdrain installation on the east end of the project.
Ripton – A streambank stabilization project continues on VT 125. Lane closures regulated by temporary traffic signals are in operation at two locations within the project area. Delays will result. Lane restrictions of 10-feet wide are in effect within the closure areas.
South Hero – An intersection improvement project is underway at U.S. 2 and VT 314. Motorists should expect speed reductions throughout the project area. Starting 07/11, the segment of U.S. 2 between VT 314 and 510 U.S. 2 will be reduced to one-way alternating traffic. Traffic will then be shifted to the east onto an on-site detour parallel to U.S. 2.
Stockbridge – A slope stabilization project continues along VT 107 between its intersections with Stony Brook Rd. and Mt. Hunger Rd. Motorists can expect one-way alternating traffic in the project area.
Swanton – A paving project is set to begin along VT 78. Motorists may encounter flaggers and minor delays as crews conduct shoulder berm removal.
Swanton – Highgate – Motorists should see little delay on U.S. 7 as crews install traffic signs, rumble strips, and pavement markings and work on site cleanup throughout the project area.
Weathersfield – Motorists will encounter areas of one-way alternating traffic along VT 131 as crews work on various activities related to a paving project.
Weston – Ludlow – A paving project is set to begin along VT 100 starting at its intersection with VT 155 progressing northeast toward Ludlow. Motorists will encounter one-way alternating traffic with some delays.
Williston Intersection Projects – Motorists will encounter lane shifts near the intersection of U.S. 2 and Industrial Ave. for an intersection improvement project. Expect one lane of alternating traffic on U.S. 2 from 7 p.m. to 6 a.m., Sunday - Thursday.
Travelers can also expect night work on VT 2A from Hurricane Lane to Taft Corners, with a lane closure in the northbound and southbound right turn lanes between 8 p.m. and 6 a.m., Monday - Friday. Minimal interruptions during daytime hours.
Williston Park and Ride – Construction of a new park and ride facility along VT 2A near the I-89 Exit 12 interchange is underway. Alternating traffic on VT 2A is possible throughout the week between 9 a.m. – 4 p.m.
Wilmington – Brattleboro – A resurfacing project continues on VT 9. Motorists can expect alternating one-way traffic in Marlboro and Brattleboro as crews conduct roadway excavation, continue the first reclamation pass, and continue paving activities.
Winooski – A roadway project continues along East Allen St./VT 15. Motorists should expect one-way alternating traffic during nighttime operations, 7 p.m. – 6 a.m., Sunday - Thursday.
Woodford – A ledge stabilization project is underway on VT 9. Intermittent traffic holds are anticipated throughout the week. A 15-minute traffic hold is planned for Thursday, 7/14 between 10 a.m. - 2:00 p.m. for blasting operations. Longer delays may occur. Eastbound traffic is reduced to one lane; a lane shift for westbound traffic will be in place through November. Motorists are urged to lower speeds when coming down the hill into the project area. A speed reduction to 35 mph is in place.
Woodstock – Hartland – A paving project begins along U.S. 4. Motorists can expect alternating one-way traffic as crews begin excavation activities.