Towns, cities |
Roads affected |
Project description |
Start date |
Completion date |
|
Alburgh, North Hero |
US 2 |
Deck replacement on |
2022 |
November |
|
Barre City |
VT 14 |
Improvement of intersection |
April |
October |
|
Barre Town |
VT 110 |
Replacement of Jail Brook bridge |
April |
November |
|
Barre Town, Orange |
US 302` |
Culvert replacement |
April |
May |
|
Barton to Lyndon |
I-91 |
Repaving, both directions and |
2022 |
November |
|
Belvidere |
VT 109 |
Replacement of PID |
June |
October |
|
Belvidere, Cambridge |
VT 109 |
Replacement of culverts |
July |
July |
|
Bennington |
US 7 |
Resurfacing, including approaches, |
April |
2024 |
|
Bennington |
VT 279 |
Resurfacing, including approaches, |
April |
2024 |
|
Bennington, Pownal |
VT 7 |
Resurfacing, 10.1 miles |
April |
2024 |
|
Berlin |
US 302 |
Replacement of Stevens Branch bridge |
March |
November |
|
Brattleboro |
I-91 |
Maintenance of West River bridge |
September |
November |
|
Brattleboro |
I-91 |
Maintenance of West River bridge |
April |
June |
|
Brattleboro |
I-91 |
Maintenance of bridges, northbound and southbound over US 5 at Exit 1 |
September |
2024 |
|
Brattleboro |
VT 142 |
Replacement of Vermont- |
2021 |
2024 |
|
Bridport |
VT 125 |
Replacement of culverts |
February |
August |
|
Brighton to Bloomfield |
VT 105 |
Repaving and resurfacing, 15.9 miles |
April |
October |
|
Burke, Lyndon |
US 5 |
Replacement of culverts, repaving, |
March |
October |
|
Burlington |
US 7 |
Construction of roundabout at Shelburne St.-S. Willard St. intersection |
2021 |
June |
|
Burlington |
US 2, US 7 |
Repaving, approximately 7 miles |
2022 |
November |
|
Cambridge |
VT 108 |
Maintenance of bridge just east of |
May |
November |
|
Cambirdge, Johnson |
VT 15 |
Rehabilitation and replacement |
May |
June |
|
Cambridge, Johnson |
VT 15 |
Repaving, 9.3 miles |
November |
2025 |
|
Castleton |
VT 4A |
Paving of bridge near Ira town line |
2022 |
June |
|
Castleton |
VT 4A |
Repair of bridge at Piontek Road |
November |
2024 |
|
Chester |
VT 103 |
Williams River bridge repair |
2022 |
June |
|
Colchester |
US2/7, I-89 |
Reconstruction of interchange 16 |
January |
2026 |
|
Colchester, Essex |
VT 2A |
Resurfacing, approximately 5 miles |
2022 |
June |
|
Coventry to Barton |
US 5 |
Repaving, 9.6 miles |
June |
October |
|
Derby to Barton |
I-91 |
Repaving, both directions and |
April |
September |
|
East Montpelier |
VT 14 |
Maintenance of bridge adjacent to |
April |
June |
|
Essex |
VT 289 |
Resurfacing, 3.9 miles, including |
2022 |
June |
|
Essex Junction |
VT 2A, VT 15, VT 117 |
Construction of 2A-117 connector, improvement of 15-117 connector |
April |
2024 |
|
Georgia, Milton |
US 7 |
Repaving, approximately 4 miles |
April |
June |
|
Grafton |
VT 121 |
Replacement of Saxtons River bridge |
September |
2024 |
|
Grand Isle, North Hero |
US 2 |
Replacement of Lake Champlain bridge |
2018 |
June |
|
Granville |
VT 100 |
Maintenance of Alder Meadow |
July |
October |
|
Hardwick |
VT 16 |
Maintenance of Greensboro Brook bridge |
2022 |
June |
|
Hardwick |
VT 15 |
Repair of Millard Brook bridge |
2022 |
June |
|
Hartford |
I-89 |
Rehabilitation and widening of |
2020 |
2026 |
|
Hartford |
US 4 |
Rehabilitation of Quechee Gorge bridge |
June |
2026 |
|
Hartford |
I-89 |
Maintenance of White River bridge |
July |
November |
|
Hartland |
US 5, VT 12 |
Reconstruction of intersection |
May |
November |
|
Jamaica, Wardsboro |
VT 100 |
Replacement of culverts, resurfacing, |
May |
October |
|
Killington |
US 4 |
Replacement of Ottauquechee |
April |
October |
|
Killington |
US 4 |
Replacement of culvert near |
April |
October |
|
Lyndon |
US 5 |
Improvements to railroad crossing |
July |
2024 |
|
Marshfield to Danville |
US 2 |
Resurfacing, 16.2 miles |
May |
2025 |
|
Marshfield to Peacham |
VT 232 |
Repaving, 6.2 miles |
May |
October |
|
Milton |
US 7 |
Bridge maintenance |
April |
June |
|
Montgomery |
VT 118 |
Replacement of Trout River and |
2022 |
June |
|
Montpelier |
US 2 |
Repaving, 4.5 miles |
May |
October |
|
Montpelier |
US 302 |
Repaving, 0.8 miles |
May |
October |
|
Montpelier |
US 2 |
Improvements to railroad crossing |
2022 |
May |
|
Montpelier to Brookfield |
I-89 |
Resurfacing, northbound only, |
April |
September |
|
Morgan |
VT 111 |
Replacement of culvert at Webster Brook |
April |
October |
|
Newfane to Brattleboro |
VT 30 |
Resurfacing, 9.9 miles |
2022 |
October |
|
Newport Town |
VT 105 |
Replacement of culvert near Potvin Rd. |
Uncertain |
October |
|
Norwich |
VT 10A |
Rehabilitation of Connecticut |
April |
November |
|
Norwich |
VT 10A |
Replacement of traffic signals |
2022 |
May |
|
Pittsford |
US 7 |
Replacement of Furnace Brook bridge |
October |
2025 |
|
Plymouth |
VT 100 |
Replacement of Black River bridge |
April |
October |
|
Randolph |
VT 14 |
Maintenance of Bloisdell Brook bridge |
July |
October |
|
Richford |
VT 105 |
Replacement of Loveland Brook bridge |
2022 |
June |
|
Richmond |
US 2 |
Replacement of bridge over I-89 |
June |
2025 |
|
Richmond, Bolton |
US 2 |
Resurfacing, 8.2 miles |
June |
2024 |
|
Rockingham |
US 5 |
Maintenance of Little Commissary |
July |
October |
|
Rockingham |
VT 103 |
Culvert replacement near Bartonsville |
June |
September |
|
Royalton |
VT 14 |
Replacement of railroad bridge over highway |
April |
2024 |
|
Royalton |
I-89 |
Rehabilitation of bridge over VT 107 |
September |
2026 |
|
Rutland City |
US 7/4 |
Improvement of intersection |
August |
2024 |
|
St Albans Town, Sheldon |
VT 105 |
Replacement of culverts |
April |
May |
|
St Albans Town, Fairfax |
VT 104 |
Replacement of culverts, repaving, |
June |
2024 |
|
St Johnsbury |
US 5 |
Bike and pedestrian improvements |
July |
2024 |
|
St Johnsbury to Fairlee |
I-91 |
Rehabilitation of 16 bridges |
2022 |
October |
|
South Burlington |
US 2 |
Traffic signal upgrades at |
2022 |
December |
|
South Burlington to Charlotte |
US 7 |
Resurfacing, 10.2 miles |
2022 |
October |
|
Springfield |
US 5 |
Replacement of culverts |
July |
October |
|
Springfield, Westminster |
I-91 |
Resurfacing, northbound lanes |
May |
October |
|
Stockbridge to Bethel |
VT 107 |
Repaving, 10 miles |
May |
October |
|
Stowe |
VT 100, 108 |
Installation of new traffic lights |
2022 |
June |
|
Stowe |
VT 108 |
Replacement of culvert at Lull's Creek |
August |
August |
|
West Fairlee, Thetford |
VT 113 |
Replacement of bridge at town line |
March |
October |
|
Westminster |
I-91 |
Repair of bridges over VT 121 |
2022 |
2024 |
|
Westminster |
I-91 |
Maintenance of Kirn Hattin Rd. bridge |
August |
2024 |
|
Whitingham, Halifax |
VT 112 |
Resurfacing, approximately 8 miles |
2022 |
May |
|
Williston |
US 2 |
Resurfacing, 1.1 miles; reconstruction of Industrial Ave. intersection |
2021 |
October |
|
Williston |
VT 2A |
Park-and-ride construction |
2022 |
August |
|
Wilmington to Brattleboro |
VT 9 |
Resurfacing, 12.6 miles |
2021 |
August |
|
Winooski |
US 2/7, VT 15 |
Repaving within city limits, |
2022 |
June |
|
Wolcott |
VT 15 |
Maintenance of Lamoille River bridge |
April |
June |
|
Woodford |
VT 9 |
Stabilization of rock-cut |
2021 |
May |
Information from Vermont Agency of Transportation. Dates reflect the time window for construction, not the precise time or duration of the work. Compiled by C.B. Hall.