2023 Vtrans Construction Projects

Towns, cities

Roads

affected

Project description

Start date

Completion date

Alburgh, North Hero

US 2

Deck replacement on
Alburgh Passage bridge

2022

November

Barre City

VT 14

Improvement of intersection
with Merchant Street

April

October

Barre Town

VT 110

Replacement of Jail Brook bridge

April

November

Barre Town, Orange

US 302`

Culvert replacement

April

May

Barton to Lyndon

I-91

Repaving, both directions and
all ramps, 20.1 miles

2022

November

Belvidere

VT 109

Replacement of PID

June

October

Belvidere, Cambridge

VT 109

Replacement of culverts

July

July

Bennington

US 7

Resurfacing, including approaches,
1.9 miles

April

2024

Bennington

VT 279

Resurfacing, including approaches,
6.1 miles

April

2024

Bennington, Pownal

VT 7

Resurfacing, 10.1 miles

April

2024

Berlin

US 302

Replacement of Stevens Branch bridge

March

November

Brattleboro

I-91

Maintenance of West River bridge

September

November

Brattleboro

I-91

Maintenance of West River bridge

April

June

Brattleboro

I-91

Maintenance of bridges, northbound and southbound over US 5 at Exit 1

September

2024

Brattleboro

VT 142

Replacement of Vermont-
New Hampshire bridges

2021

2024

Bridport

VT 125

Replacement of culverts

February

August

Brighton to Bloomfield

VT 105

Repaving and resurfacing, 15.9 miles

April

October

Burke, Lyndon

US 5

Replacement of culverts, repaving,
approximately 7 miles

March

October

Burlington

US 7

Construction of roundabout at Shelburne St.-S. Willard St. intersection

2021

June

Burlington

US 2, US 7

Repaving, approximately 7 miles

2022

November

Cambridge

VT 108

Maintenance of bridge just east of
Desjardin Road

May

November

Cambirdge, Johnson

VT 15

Rehabilitation and replacement
of culverts

May

June

Cambridge, Johnson

VT 15

Repaving, 9.3 miles

November

2025

Castleton

VT 4A

Paving of bridge near Ira town line

2022

June

Castleton

VT 4A

Repair of bridge at Piontek Road

November

2024

Chester

VT 103

Williams River bridge repair

2022

June

Colchester

US2/7, I-89

Reconstruction of interchange 16

January

2026

Colchester, Essex

VT 2A

Resurfacing, approximately 5 miles

2022

June

Coventry to Barton

US 5

Repaving, 9.6 miles

June

October

Derby to Barton

I-91

Repaving, both directions and
all ramps, 12.9 miles

April

September

East Montpelier

VT 14

Maintenance of bridge adjacent to
North Montpelier Pond

April

June

Essex

VT 289

Resurfacing, 3.9 miles, including
ramps and spurs

2022

June

Essex Junction

VT 2A, VT 15, VT 117

Construction of 2A-117 connector, improvement of 15-117 connector

April

2024

Georgia, Milton

US 7

Repaving, approximately 4 miles

April

June

Grafton

VT 121

Replacement of Saxtons River bridge

September

2024

Grand Isle, North Hero

US 2

Replacement of Lake Champlain bridge

2018

June

Granville

VT 100

Maintenance of Alder Meadow
Brook bridge

July

October

Hardwick

VT 16

Maintenance of Greensboro Brook bridge

2022

June

Hardwick

VT 15

Repair of Millard Brook bridge

2022

June

Hartford

I-89

Rehabilitation and widening of
Vermont-New Hampshire bridges

2020

2026

Hartford

US 4

Rehabilitation of Quechee Gorge bridge

June

2026

Hartford

I-89

Maintenance of White River bridge

July

November

Hartland

US 5, VT 12

Reconstruction of intersection

May

November

Jamaica, Wardsboro

VT 100

Replacement of culverts, resurfacing,
11 miles

May

October

Killington

US 4

Replacement of Ottauquechee
River bridge

April

October

Killington

US 4

Replacement of culvert near
Sherburne Center

April

October

Lyndon

US 5

Improvements to railroad crossing
in Lyndonville

July

2024

Marshfield to Danville

US 2

Resurfacing, 16.2 miles

May

2025

Marshfield to Peacham

VT 232

Repaving, 6.2 miles

May

October

Milton

US 7

Bridge maintenance

April

June

Montgomery

VT 118

Replacement of Trout River and
West Hill Brook bridges

2022

June

Montpelier

US 2

Repaving, 4.5 miles

May

October

Montpelier

US 302

Repaving, 0.8 miles

May

October

Montpelier

US 2

Improvements to railroad crossing

2022

May

Montpelier to Brookfield

I-89

Resurfacing, northbound only,
including ramps, 15.6 miles

April

September

Morgan

VT 111

Replacement of culvert at Webster Brook

April

October

Newfane to Brattleboro

VT 30

Resurfacing, 9.9 miles

2022

October

Newport Town

VT 105

Replacement of culvert near Potvin Rd.

Uncertain

October

Norwich

VT 10A

Rehabilitation of Connecticut
River bridge

April

November

Norwich

VT 10A

Replacement of traffic signals

2022

May

Pittsford

US 7

Replacement of Furnace Brook bridge

October

2025

Plymouth

VT 100

Replacement of Black River bridge

April

October

Randolph

VT 14

Maintenance of Bloisdell Brook bridge

July

October

Richford

VT 105

Replacement of Loveland Brook bridge

2022

June

Richmond

US 2

Replacement of bridge over I-89

June

2025

Richmond, Bolton

US 2

Resurfacing, 8.2 miles

June

2024

Rockingham

US 5

Maintenance of Little Commissary
Brook bridge

July

October

Rockingham

VT 103

Culvert replacement near Bartonsville

June

September

Royalton

VT 14

Replacement of railroad bridge over highway

April

2024

Royalton

I-89

Rehabilitation of bridge over VT 107
and White River

September

2026

Rutland City

US 7/4

Improvement of intersection
with Cold River Rd.

August

2024

St Albans Town, Sheldon

VT 105

Replacement of culverts

April

May

St Albans Town, Fairfax

VT 104

Replacement of culverts, repaving,
1.7 miles

June

2024

St Johnsbury

US 5

Bike and pedestrian improvements
(also on Main Street)

July

2024

St Johnsbury to Fairlee

I-91

Rehabilitation of 16 bridges
(8 in Bradford), both directions

2022

October

South Burlington

US 2

Traffic signal upgrades at
I-89 interchange

2022

December

South Burlington to Charlotte

US 7

Resurfacing, 10.2 miles

2022

October

Springfield

US 5

Replacement of culverts

July

October

Springfield, Westminster

I-91

Resurfacing, northbound lanes
and ramps, 14.9 miles

May

October

Stockbridge to Bethel

VT 107

Repaving, 10 miles

May

October

Stowe

VT 100, 108

Installation of new traffic lights
at intersection

2022

June

Stowe

VT 108

Replacement of culvert at Lull's Creek

August

August

West Fairlee, Thetford

VT 113

Replacement of bridge at town line

March

October

Westminster

I-91

Repair of bridges over VT 121

2022

2024

Westminster

I-91

Maintenance of Kirn Hattin Rd. bridge

August

2024

Whitingham, Halifax

VT 112

Resurfacing, approximately 8 miles

2022

May

Williston

US 2

Resurfacing, 1.1 miles; reconstruction of Industrial Ave. intersection

2021

October

Williston

VT 2A

Park-and-ride construction
at I-89 intersection

2022

August

Wilmington to Brattleboro

VT 9

Resurfacing, 12.6 miles

2021

August

Winooski

US 2/7, VT 15

Repaving within city limits,
approximately 2 miles

2022

June

Wolcott

VT 15

Maintenance of Lamoille River bridge
near Turcotte Road

April

June

Woodford

VT 9

Stabilization of rock-cut

2021

May

Information from Vermont Agency of Transportation. Dates reflect the time window for construction, not the precise time or duration of the work. Compiled by C.B. Hall.