Drawbirdge Facts
The temporary drawbridge is opening on the top of the hour between 8 AM and 8 PM, 7 days per week, until October 15, 2019. An update for this boating season includes a reduction in channel width to 40 feet at the drawbridge location.
The existing bridge is left in the open position. Mariners can request drawbridge openings by the bridge tender on Channel 13 or at 802-372-4360. The bridge will not open unless a request is made.
The Vermont Agency of Transportation (VTrans) is replacing Bridge 8 on US 2 between the towns of North Hero and Grand Isle, Vermont. This drawbridge is a historic twin leaf bascule bridge, and the only vehicular movable bridge in the State of Vermont. Construction began in June 2018 and the estimated completion date is in 2022. The contractor will build a temporary drawbridge prior to replacing the existing drawbridge so that impacts to vehicular traffic are minimized.
-
July to August 2018: one-lane, two-way traffic on the existing drawbridge
-
August 2018 to May 2019: two lane, two-way traffic on the existing drawbridge
-
May 2019 to May 2021: two lane, two-way traffic on the temporary drawbridge
-
May to September 2021: two lane, two-way traffic on the new drawbridge
-
September 2021: one-lane, two-way traffic on the new drawbridge
-
October 2021: two lane, two-way traffic on the new drawbridge
For more information on construction updates at the drawbridge, click here.
The North Hero – Grand Isle drawbridge will operate on a steady schedule; opening on the top of the hour between 8 AM and 8 PM, 7 days per week, from May 15 thru October 15, 2018. The drawbridge will be greased weekly on Monday mornings, requiring the bridge to be open between 6 AM and 6:30 AM every Monday.